How was the Eisenhower Tunnel built?

Written by

in

Last updated: November 19, 2026.

How do you dig a road through the top of the Rocky Mountains? Colorado engineers had to find out the hard way. The Eisenhower Tunnel carries Interstate 70 under the Continental Divide, about 60 miles west of Denver. People thought it would take three years to build. It took five.

While it was being dug, the tunnel had a different name: the Straight Creek Tunnel, after the valley where its west end is found. Today it is the highest vehicle tunnel in the United States.

Quick facts

📍

Where

About 60 miles west of Denver, under the Continental Divide on Interstate 70.

📏

How long

The first bore, the Eisenhower bore, is 1.693 miles long.

⛰️

How high

The west end sits at 11,158 feet above sea level.

⏱️

How long it took

Planned for three years. Built in five, starting March 15, 1968.

💡 Did you know? Before the tunnel opened, a driver slipped past the “no traffic” signs and drove through the mud inside it. He got a ticket for trespassing, but the judge threw the charge out because the signs had not been clear enough.

Timeline of the tunnel

1963–1965

A small pilot tunnel is dug first, through the same mountain.

March 15, 1968

Work begins on the first big bore.

September 1969

Governor John Love suggests naming the tunnel for President Eisenhower, who had died that April.

1972

The Colorado legislature officially chooses the Eisenhower name.

March 8, 1973

The tunnel is dedicated and opens to traffic.

August 1975

Work starts on the second bore.

December 21, 1979

The second bore, named for Governor Edwin C. Johnson, opens.

Why did the engineers want a tunnel?

Before the tunnel, cars and trucks had to climb over Loveland Pass on U.S. Highway 6. The road is steep, twisty and often closed by snow. When Colorado and the federal government planned Interstate 70 across the state, engineers decided that tunneling under the pass would work better than trying to build a modern highway over it.

Four things that made it hard

The state highway department said it plainly: the crews were fighting the mountain, the weather and the height.

  • The air. Men and machines worked less well at about eleven thousand feet.
  • The winter. Snow kept the outdoor working season painfully short.
  • The rock. Fault lines in the mountain had not shown up in the small pilot tunnel. Parts of the rock slipped while the crews dug, so engineers had to rush in extra supports to protect the workers.
  • The size. The tunnel is about fifty feet high and forty-five feet wide, so new ways of digging and holding up the roof had to be invented.

One veteran highway engineer put it like this: they had gone by the book, but the mountain could not read.

The people and the numbers

According to the Federal Highway Administration, nearly 6,000 people worked on the project at various times over five years. Together they put in about 4.9 million hours of work and cut through 7,789 feet of rock and earth under the Continental Divide. The job was run by a team of four construction companies called Straight Creek Constructors.

It was also a very costly job. The first estimate for the Eisenhower bore was $42 million, but it ended up costing $108 million. Most of the money came from the federal government. Three men lost their lives working on the first bore, which is a reminder that tunnel work was dangerous.

Quick questions

Was the tunnel always called the Eisenhower Tunnel?

No. During construction it was the Straight Creek Tunnel. President Dwight D. Eisenhower died on April 4, 1969, and Governor John Love soon proposed the new name. The state legislature made it official in 1972.

How cold was it at the opening?

About 34 degrees Fahrenheit, with some snow flurries. The ceremony on March 8, 1973 was held inside the tunnel, at the east end, because of the weather.

Is the old road over the pass still used?

Yes. Trucks carrying dangerous materials and some tall trucks are not allowed in the tunnel, so they still take Loveland Pass. Bicycles and walkers must use the pass too.

After the opening

Traffic was heavier than planners had expected. The first bore carried cars in both directions, one lane each way, so work soon began on a second bore for eastbound traffic. When it opened in 1979, the tunnel finally had two lanes in each direction. When the Eisenhower bore opened, it became the highest vehicle tunnel in the world. Today it is the longest mountain tunnel and the highest point on the U.S. Interstate Highway System.

What is real and what is made up

Every date and number on this page is real history from the sources below.

Book 8 of TRACE in Colorado is a made-up time-travel adventure that visits Colorado in 1893 and 1970. Its characters and story are invented. The history of the tunnel is real.

This story comes from TRACE in Colorado by T. A. Held, a time-travel series for ages 9 to 14 with a What Was Real? page in every book.

Read the series: Book 8 of TRACE in Colorado · See all the TRACE in Colorado books

Previous post: Space race and 1970s books for kids

Next post: Janet Bonnema, the first woman in the Eisenhower Tunnel

Comments

Leave a Reply

Please use your first name or a nickname only. Don’t share your full name, address, school, or email. Every comment is read before it appears.