What happens when a giant bridge is built the wrong way around? In Colorado in 1883 workers finished the Devil’s Gate High Bridge for the Georgetown Loop, and the chief engineer said no. The crew had to take it apart and put it back together in the middle of winter.
Quick facts
📏
Length
The bridge was about 300 feet long.
🧗
Height
It rose about 95 feet above Clear Creek.
🏗️
Towers
Four iron towers, from 33 to 78 feet tall, stood on sixteen granite piers.
🏭
Builder
The Phoenixville Bridge Company of Pennsylvania made and raised the bridge.
💡 Did you know? When the bridge was rebuilt in 1984, the tower legs were made thicker than the originals. The old legs were 8 inches across, and the new ones are 12 and 14 inches, to meet today’s safety rules.
Building the bridge
October 4, 1883
The stone piers are finished. The next day the first car loaded with iron arrives in Georgetown.
November 29, 1883
The first version of the bridge is done.
Late 1883
The chief engineer refuses it. Talks with the bridge company go on for several weeks.
January 24, 1884
The repaired bridge is completed.
February 28, 1884
The first test locomotive crosses.
The problem
The Devil’s Gate High Bridge was the most important part of the Georgetown Loop. It crossed the narrowest part of the valley and made the upper level of the loop. The Union Pacific Railroad hired the Phoenixville Bridge Company to build it on a curve that rose gently, about 2 feet for every 100 feet of track.
By the end of November 1883 the work looked finished. Then the chief engineer, Robert Stanton, checked it. He refused to accept the bridge. He said the riveting was poor, and that the north and south columns of the bridge had been put in the wrong places. One historical account puts it more simply: the whole bridge had been put up backwards.
The fix
Nobody was blamed by name in the sources we found. The bridge company was responsible, and after several weeks of talks it agreed to make the changes. Workers took the bridge apart and put it back together again. One account calls it a six-week job in the dead of winter, in the Colorado mountains. The repaired bridge was completed on January 24, 1884. On February 28 a test locomotive crossed it. Read about the engineer in Robert Brewster Stanton, the engineer of the Georgetown Loop.
We could not find out exactly why the pieces were put up the wrong way. It is a mystery of the Loop that sources do not explain.
The bridge in numbers
The 300 feet of bridge were made of eight short spans, each 30 feet long, and one longer 60-foot span in the middle. The high bridge sat 75 feet above the lower track it crossed. The towers stood on sixteen stone piers, one under each leg. Even with all that iron, the bridge was only about 9.8 feet wide, just wide enough for one narrow-gauge track.
What happened to the bridge
When the railroad closed, the high bridge was taken down in 1939 and sold as scrap iron. The new bridge of 1984 follows the old design. Two things changed to meet modern safety rules. The tower legs are thicker, and the base piers are solid concrete instead of granite with rubble fill.
How to picture it
Imagine a tall iron table with four tall legs standing in a canyon, and a railroad track running across the top. Now imagine that when the legs were set, two were swapped. The track would look fine from far away, but the engineer who checks every part would still say no.
What is real and what is made up
The Devil’s Gate High Bridge was real, and so were the dates, the sizes and the engineer’s refusal on this page.
Loop Around, Book 7 of TRACE in Colorado, is a made-up story. The people in the book are invented.
This story comes from TRACE in Colorado by T. A. Held, a time-travel series for ages 9 to 12 with a What Was Real? page in every book.
Read the book: Loop Around (Book 7) · See all the TRACE in Colorado books